Weld is over capacity. Fix it without hiring.
A five-step bracket line ships 460 parts a day. Weld needs 125 s per part against a 120 s takt, so it runs at 112% of its capacity. The 600 finished parts in stock hide it for three weeks; then orders start shipping short.
- Simulate 60 days. Orders ship complete on only 60% of days, and a backlog of 1,163 parts builds up.
- Open Suggestions. First on the list: move 30 s of Weld's work to the Powder Coat operator, who waits on the machine for most of each cycle.
- Test it. The same 60 days, same demand and breakdowns, with and without the change.